National Irrigation System Development Project


New Deirout Barrages Project


An integrated project to develop the irrigation system in Middle Egypt, improve water management and distribution efficiency, and serve agricultural lands across five governorates.


Project Overview


The New Deirout Barrages Project aims to improve irrigation conditions across an area of approximately 1.6 million feddans, representing around 20% of Egypt’s old agricultural lands, and serving the Middle Egypt region across the governorates of Assiut, Minya, Beni Suef, Fayoum, and Giza.

The project focuses on developing the barrages system and improving the control of water discharges and levels, contributing to better water management and distribution and enhancing the efficiency of the irrigation system in the region.

”Project


Project at a Glance

”1.6

5 Governorates

Assiut, Minya, Beni Suef, Fayoum, and Giza

38 Monitoring Stations

For monitoring and tracking water discharges and levels

99.1%

Completion rate as of March 2026


Project Objectives

”Improved

Improved Water Management

Provide a modern system for monitoring water discharges and levels and supporting decision-making.

Preserving Heritage

Preserve the historic barrages complex, which was established more than 150 years ago.

Developing the Surrounding Area

Improve and landscape the project area in a manner reflecting its historical and engineering significance.

”Improving


Project Components

An integrated system for barrages development and water management

New Barrages Complex

The new complex consists of barrages serving a number of main intakes and canals, including Bahr Youssef Head Regulator, Ibrahimia Head Regulator, Badraman Head Regulator, Deiroutia Head Regulator, Abu Gabal Head Regulator, Dalgawi Irrigation Intake, and Sahelia Intake.

Monitoring and Control System

A system for monitoring water discharges and levels, comprising 38 monitoring stations, in addition to a main station at the Deirout Barrages Complex control building and a sub-monitoring station at the Water Distribution Administration in Assiut.


Project Timeline

”7

48 Months

Original project implementation period

28 February 2026

New barrages complex became operational

15 June 2026

Revised completion date published on the project page


Implementation Status


The project had reached 99.1% completion as of March 2026, according to the information published on the project page.

The new barrages complex was completed and became operational on 28 February 2026. The water discharge and level monitoring system was also completed, with trial operation beginning on 30 March 2026.

Training activities for the operation and maintenance of the project components also commenced in accordance with the operation and commissioning plan.

99.1%

Completion rate as of March 2026


Additional Works

”Security

Site Landscaping and Beautification

”Alternative


Key Project Information

”Project

Project Contractor

Dai Nippon Construction of Japan

Project Cost

JPY 5,854 million
+ EGP 700 million