Siwa Oasis Development Project

Restoring the water and environmental balance of Siwa Oasis through the development of irrigation and drainage systems, rationalizing water use, and protecting agricultural land and local communities.

EGP 3 Billion

Total value of the development works

3 Phases

For developing the irrigation and drainage system
image

Siwa Oasis

An oasis of environmental, agricultural, and tourism importance, Siwa has faced challenges over the past decades related to rising agricultural drainage water levels, water salinity, and excessive groundwater abstraction.

5 Villages

The oasis includes five villages and their surrounding settlements.

320 km

Approximately southwest of Marsa Matrouh.

Water Balance

Improved management of water resources and drainage levels.

Project Objectives

Lowering Water Levels

Lower agricultural drainage water levels in Siwa and Bah El-Din Lakes.

Protecting Agricultural Land

Reduce the impact of rising groundwater levels and salinity on agricultural land.

Water Conservation

Achieve a balance between water abstraction rates and safe water levels.

Oasis Sustainability

Protect the oasis’s water and environmental resources for future generations.

Water Management System

Integrated solutions combining wells, irrigation networks, pumping stations, and drainage systems

Deep Water Wells

Drilling deep wells to produce freshwater and improve the utilization of available water resources.

Water Distribution Networks

Developing irrigation water distribution networks and connecting them to new water sources.

Drainage System

Conveying agricultural drainage water away from agricultural lands and areas affected by rising water levels.

The Project in Numbers

EGP 3 Billion

Total value of the project phases

12 Wells

Deep production wells

60,000 m³/day

Capacity of the Phase II pumping station

34 km

Open canal extending to Ain El-Ganbi Depression

Environmental, Economic and Social Impact

Environmental

Addressing rising drainage water levels and salinity while protecting the oasis’s agricultural lands and water resources.

Economic

Supporting agricultural production, improving the utilization of water resources, and enhancing services and infrastructure.

Social

Supporting stability for oasis communities, addressing agricultural drainage challenges, and improving quality of life.

Project Implementation Phases

Phase One

2021

12 deep production wells with a depth of approximately 1,200 meters.

9 irrigation water distribution networks.

Rehabilitation of the existing irrigation system.

Reinforcement of Siwa Lake embankments over 14 km.

Closure of highly saline shallow wells.

Phase Two

2022

Pumping station with a capacity of 60,000 m³/day.

Two polyethylene pipelines with a total length of 6 km.

Construction of a stilling basin.

34 km open canal.

Diversion of four drains with a total length of 7.5 km.

Phase Three

2024

Al-Ghazalat pumping station with a capacity of 20,000 m³/day.

Installation of suction and discharge pipelines.

Reinforcement of Siwa and Bah El-Din Lake embankments.

New distribution networks.

6 mesqas with a total length of approximately 110 km.

Phase One

Phase One included the construction of deep production wells and irrigation water distribution networks, together with improving the existing irrigation system and reinforcing the embankments surrounding Siwa Lake.

Key Works

12 deep production wells
9 distribution networks
Irrigation system rehabilitation
Rehabilitation of the level-control station reservoir
Operation of the Al-Kaf pumping station using solar energy
14 km of embankments

Phase Two | Drainage System

EGP 1.3 Billion

Pumping station with a capacity of 60,000 m³/day.

Two polyethylene pipelines with a total length of 6 km.

34 km open canal.

Diversion of four drains with a total length of 7.5 km.

Phase Three | System Completion

EGP 1 Billion

Al-Ghazalat pumping station with a capacity of 20,000 m³/day.

Reinforcement of Siwa and Bah El-Din Lake embankments.

4 distribution networks.

6 mesqas with a total length of approximately 110 km.

Water Sustainability… Oasis Sustainability

The development of Siwa Oasis represents an integrated approach combining water management, environmental protection, agricultural support, and improved quality of life, helping ensure the sustainability of the oasis’s water and environmental resources.